Education




                                                                default. For example, without a tornado, I would have de-
                                                                livered the garden shed you ordered. Because of the tor-
                                                                nado, I can't, because it blew away.

                                                                Force majeure clauses in contracts are included to provide
                                                                one or more parties to an agreement relief from their ob-
                                                                ligations should certain circumstances arise. The event
                                                                contributing to the application of the force majeure clause
                                                                should not only be unforeseeable, but also beyond the con-
                                                                trol of the parties.
        Force majeure                                           Unforeseeable here, means unforeseeable at the time the


                                                                contract was entered into. As in the typical clause ex-
        clauses – never                                         ample above, force majeure clauses outline the types of
                                                                situations where the clause may excuse non-performance.
        read until now                                          Since such clauses are a construct of the parties, the mean-
                                                                ing and scope shall be those given by the parties in cre-
                                                                ating the agreement. Where clauses are lacking or where
        By Adam Atlas                                           there is room for interpretation, courts will apply common
                                                                law principles.
        Attorney at Law
                                                                What if the force majeure clause
                 adly, because of the COVID-19 pandemic,        does not list pandemic?
                 some participants in the payments industry are
                 unable to meet their contractual obligations.   Many drafters of force majeure clauses include catch-all
        S The purpose of this article is to give some guid-     phrases to extend the provision to non-enumerated situa-
        ance to people on either side of that terrible turn of events.  tions by including words such as "other," etc. Courts tend
                                                                to apply the ejusdem generis (Latin for "of the same kind")
        Specifically, I want to discuss force majeure clauses, which   theory when determining if a given situation fits within
        are most likely to apply to a pandemic-caused contractual   the catch all phrasing.
        default. Simply put, when it comes to the law, force majeure
        pertains to unforeseeable circumstances that prevent    Ejusdem generis dictates that when general terms follow
        someone from fulfilling a contract.                     an enumerated list of two or more items, then the general
                                                                terms must apply only to items of the same class as those
        Force majeure clause                                    enumerated. The potential application of ejusdem generis
                                                                to a force majeure clause must be kept in mind not only
        Force majeure clauses in contracts are usually buried in   when drafting such clauses, but also when formulating
        the general provisions and are rarely negotiated or even   argumentation to either defend or argue the non-applica-
        read. The pandemic has suddenly given great importance   bility of a force majeure clause.
        of force majeure clauses.
                                                                When analyzing force majeure clauses, courts will often
        A typical force majeure clause in a payment processing   ask three questions:
        agreement reads as follows:
                                                                   1. Is the event in question a force majeure event (as de-
           "Force Majeure. No Party shall be liable for any default   fined by the clause)?
           in the performance of its obligations under this
           Agreement if such default or delay is caused, directly   2. Was the event beyond the reasonable control of the
           or indirectly, by an Act of God, fire, flood, earthquake,   party evoking the clause?
           conditions  or events  of  nature,  war,  terrorism,  riots,
           pestilence,  civil disturbances,  work stoppages,       3. How does the event affect the obligation the party is
           equipment failures, power failures, governmental        seeking to be excused from?
           orders, or any other similar cause or event beyond   Case Study 1: ISO can't make minimums
           the reasonable control of the affected party (provided   because of COVID-19
           the non-performing Party is without material fault in
           causing such default or delay)."                     Taking an extreme but illustrative example, if an ISO has
                                                                focused on selling merchant services to amusement parks,
        The key legal question when facing a force majeure clause   and all amusement parks are closed by order of the state,
        is to determine whether it relieves the party of default for   even if the force majeure clause in the ISO agreement does
        non-performance. In other words, but for the force ma-  not expressly mention pandemics, generic wording on fac-
        jeure event, would the failure of the party place them in   tors beyond the control of the ISO would likely support